Tasks with SP estimate, sub-tasks with Time Estimate and see both on Burndown Chart?

selcuk alimdar September 19, 2021

I assigned SP to tasks (User Stories) and activated time tracking and original estimate for sub-tasks. I can see exactly the SP burndown chart but there is problem with time burndown since the chart only considers done sub-tasks as burned.

 

As an Agile Coach, I want my team see Burndown Chart for the tasks in terms of hours burned even the tasks is still in progress, in order to optimize transparency for the sprint progress.

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 19, 2021

Sub-tasks are a part of items you commit to, they are not individual separate items in themselves.

A burn down chart measures delivery against commitment.

As an Agile Coach, you can see that means that you do not burn down on sub-tasks 

The burn-down chart will show time accrued as you log it, but it is not a burn-down