I assigned SP to tasks (User Stories) and activated time tracking and original estimate for sub-tasks. I can see exactly the SP burndown chart but there is problem with time burndown since the chart only considers done sub-tasks as burned.
As an Agile Coach, I want my team see Burndown Chart for the tasks in terms of hours burned even the tasks is still in progress, in order to optimize transparency for the sprint progress.
Sub-tasks are a part of items you commit to, they are not individual separate items in themselves.
A burn down chart measures delivery against commitment.
As an Agile Coach, you can see that means that you do not burn down on sub-tasks
The burn-down chart will show time accrued as you log it, but it is not a burn-down