If I have an iteration (sprint from JIRA agile scrum board) scheduled (e.g. over two weeks) for all team member and I add something in that time frame (custom entry or story in time line or classic view) for all team members, commitment for the iteration is not reduced but everybody is simply over committed..
When I do the same but only add something to one team member, it works and commitment for the iteration is reduced at that specific date and I also see the entry as blocking in backlog mode.
How can I do something like plan a sprint / iteration in tempo planer and then add an event to reduce the available time for the whole team for the sprint / iteration?
Hi Matthias,
this is not possible in the current version of Tempo Planner.
When a Plan is created for the whole Team, it does not automatically reduce the commitment for an existing Team plan. You will need to change the commitment for the Team manually (in Team Members Timeline, expand the existing Plan and choose "Edit". In the Dialog, you can change the commitment for the Team).
You can also create a feature request in our Tempo Planner Project (https://tempoplugin.jira.com/wiki/display/TP/Tempo+Planner+Support+Home) for this and it will be evaluated by Project management. Other users can then comment and vote on it.
Regards,
Susanne
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.