Tempo Planner: Can I get a Report that shows the Time planned for Epics?

Aron Peterseim
Contributor
May 12, 2025

@Tempo Support Hello,

Whenever we create a "planned Time" report in the Capacity Planner then Only Issues with the Task Hierarchy Level or lower are displayed

If we sort by Epic then the Epic only shows up if it already has tasks assigned to it (and even then, the total Time that is shown only shows the sum of all Parented Tasks' estimates, not the Epic's Original Estimate).

Is there a way to create a Report that shows the Planned Time of all Epics in a certain project?

1 answer

1 accepted

1 vote
Answer accepted
Dilip
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 12, 2025

For tempo support, you can reach out to vendor support team using the below link:
link - https://tempo-io.atlassian.net/servicedesk/customer/portal/6