@Tempo Support Hello,
Whenever we create a "planned Time" report in the Capacity Planner then Only Issues with the Task Hierarchy Level or lower are displayed
If we sort by Epic then the Epic only shows up if it already has tasks assigned to it (and even then, the total Time that is shown only shows the sum of all Parented Tasks' estimates, not the Epic's Original Estimate).
Is there a way to create a Report that shows the Planned Time of all Epics in a certain project?
For tempo support, you can reach out to vendor support team using the below link:
link - https://tempo-io.atlassian.net/servicedesk/customer/portal/6
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.