Having planned time on projects for team members (planning tab, choosing 25, 50, 75, 100% etc), when I navigate to the next tab titled "time tracking" there is a row for planned time... but it is still empty for each team member.
When I go to plan time in that view, the team members are still shown to be 100% available, even though in Tempos planning tab they are 100% planned, and then after adding plans there they are not then reflected in the first "planning" tab.
What am I missing?
Hi Pete,
can you inform me about the versions of Tempo Timesheets and Tempo Planner you are using as the feature of planned time showing in the timesheet is only available since the release of Tempo Timesheets 7.9. and Planner 1.2.
In case you are having this problem in these (or later) versions, please create an issue in our Tempo Support project (https://tempoplugin.jira.com/browse/JTS) so we can better investigate this. All added information and screenshots are appreciated.
Kind regards,
Susanne
Thankyou.
It didn't occur to me that this would not already be a feature. Seemed obvious to expect planned time in planner to show in the planned row in timesheets.
Just upgraded to 7.9 and as you have said, it now works.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.