Tempo Reporting - Can I use the original estimate field in Jira for reporting in Tempo

Kaneesha Gunanathan April 4, 2024

I am looking to create reports on estimated time against actual time logged by my team members in Tempo. I want to find out if I can use the field "original estimate" in Jira for reporting in Tempo.

 

I see the planned time against actual time in reporting but when if I could use the original estimate field in Jira to report the planned time. This would reduce my time of having to enter planned time seperately.

1 answer

0 votes
Susan Wu
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 4, 2024

Hi @Kaneesha Gunanathan 

You should be able to view original estimate in overview of Logged and Planned Time reports.  https://help.tempo.io/timesheets/latest/viewing-the-data-in-reports

If you need any further assistance, please contact Tempo Support directly.

https://tempo-io.atlassian.net/servicedesk/customer/portal/6

Best regards,

Susan Wu
Tempo Product Experts

Kaneesha Gunanathan April 8, 2024

Hi Susan ,

 

I don't see the overview tab in my reports. I even checked the planned and actual reports and I don't see Original Estimate in the Jira field.

 

Thanks

 

Kaneesha