Hi,
I have a large project with a combination of stories, sub-tasks, tasks, epics, bugs etc.
Recently when I run the time tracking report the figures it returns for original estimate, time spent and remaining are not correct and do not include all the issues. This is even true when I do the export of the report.
At the bottom of the report I have noticed that the following is displayed:
image2016-11-22 9:59:42.png
The thing is I need all the issues shown to me, and this report is then not fit for purpose if it does not show me everything.
Now I am having to do a filtered issue report for the same information which takes time.
Please can anyone help
Many thanks
Raya
I'm afraid it is what it says it is - you are using queries that are too large to be handled.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.