The issue in backlog showing crossed out/strike through even it is in unresolved resolution.

Deleted user March 2, 2023

In Jira, in one of the project backlog we have noticed that one of the issues showing crossed out. The Resolution will be set to Done. If we change it back to "Unresolved" the cross out continues to show on the Backlog list of issues.

1 answer

3 votes
Dave Mathijs
Community Champion
March 2, 2023

Hello @[deleted] welcome to the Atlassian Community

Make sure that statuses in To Do (grey color) / In Progress (blue color) categories clear the resolution via a post-function.