Hi,
I completed a sprint early, but I want to fix the timeline to match the date I completed the sprint, if that makes sense.
but when I do, it shows this warning: 'This parent issue ends before its child issues are scheduled to complete.'
Hi @Sara Husain , welcome to the Atlassian Community and thanks for your question.
It depends on how your Timeline is configured. If you're showing the issue due date, you should be able to do a bulk update and move the due date to all of the issues in the Sprint to today. That should clear up the view in the Timeline.
Hope this helps you.