I am currently using a team-managed project on the Cloud to run sprints. The tickets in the done column are not disappearing from the sprint once the sprint ends. How do I make the tickets disappearing once they are done and we start a new sprint?
Thanks.
Hi Chun,
Is the Done column that very last column on the board (far right)? That's the only way that the sprint will consider them completed.
Hi John, my Done column was not the last one on the sprint board. I moved it to the last. Hopefully this will work when the sprint ends. Thanks for your help!