Time Tracked on sub tasks is not appearing on Epic - Need Help

Saad Ahmad
Contributor
May 26, 2025

Hi, our team logs time on tasks and sub-tasks which are created under an epic. we want to sum them up and show on epic, but its happing even when the 'Include Sub-Task' checkbox is true.

Please guide how to fix it.

 

Time tracking.png

1 answer

0 votes
Ramakrishna _RK_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 26, 2025

Hi Ahmad,

Welcome the Community!

 

Subtasks are typically associated with standard issue types like tasks or stories, which can then be linked to an epic. Here's how the hierarchy generally works:

  1. Epic: The highest level in the hierarchy, used to group related tasks or stories.
  2. Task/Story: Standard issue types that can be linked to an epic.
  3. Subtask: A smaller unit of work that is part of a task or story

I am assuming this scenario occurred due to hierarchy miss alignment. Can you please map subtasks to Standard issuetype and then to Epic? Hope this will sum up the worklog on Epic.

 

Regards

RK

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events