Time Tracking - Is changing the # of hours/day retroactive - or only for new entries?

Matthew Lee February 2, 2023

Current setting is 6 hours per day. If I change to 8, will it automatically update existing times based on 8 hour day, or will that only apply to new (if I currently have 2 days logged, would that become 1D 4H or stay at 2D)

1 answer

0 votes
Florian Bonniec
Community Champion
February 2, 2023

Hi @Matthew Lee 

 

Not 100% sure but I think it will update the way it's displayed but data is stroed in sec so if you logged 1d before the change it will not update from 6 to 8 but it will be displayed 6h istead 1d now.

When you will log 1d it will log 8h for the new work log entries

 

Regards