Background:
We have epics with original estimates on them.
We has stories and sub-tasks below the epics with time tracking used on them.
No time tracking is done at the epic level, only the child stories and sub-tasks below them.
The time spent (calculated from time tracking) rolls up to the epic and gives us an idea of time spent vs original estimate.
However, the only way I can view this information is on the card view of the epic on a board.
In query view, the story view, backlog etc., it does not show. Not even the fields show even though they are applied in the issue screen scheme.
Any ideas on how to get this information visible in any other view other than the card itself? Or why it shows there but no where else?
Have added screenshots to show detail of the setup.