In Advanced roadmap timeline, completed issues disappearing 30 days after completion. How to keep them?
Hello @Nikita
Welcome to the Atlassian community.
Go to Plan Settings.
Select Work In Your Plan and then select the Removed Work Items tab.
Click on the View Rules option in the box that says "Based on type or status" , and a panel will appear on the right where you can set the time period for hiding Done items.
@Trudy Claspill You are the best!
Thank you, all works 👍
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You're welcome!
If you question has been adequately addressed, please consider clicking on the Accept Answer button above my response to mark your Question as Solved. That helps others searching the community find the posts with validated responses.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.