I want the Timeline gantt chart to be sequential in time.
How do I order epics by "start date" for the timeline (roadmap).
AND also include by Rank descending (so I can drag epics about too).
Hello @Steve Farrand
Welcome to the Atlassian community.
You can't do that. The Timeline feature will ordered the issues based on the ORDER BY clause of the underlying board filter. If the ORDER BY clause uses anything other than Rank, then you cannot drag and drop issues to re-order them.
You will have to manually reorder the Epics (while the ORDER BY clause uses Rank) so that they are ordered based on their Start dates.
Hi,
I wanted to order the tasks on the board by priotory and also realized that timeline also use the ranking method. Now I deleted the Epic's priority field (no field no ranking I thought) but ranks it anyway, I can't order the epics.
Now I can not make my own order of Epics because of this:
My goals:
Do you have any suggestion to solve this issue?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Prizific
Welcome to the Atlassian community.
To best leverage the community and get the most visibility for your request please start a brand new Question post.
The only people who see additions to existing Questions are the author of the original Question and the people who responded to it.
If you think this person's Question is relevant to your situation then include a link to it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.