Hi,
We need to be able to track our issues spill over from each sprint
For example,
Sprint 12 issue count = 100 and we were only able to close 80, so 20 issues will spill over to next sprint.
We would need to report the new sprint 13 issues(100) + the 20 spill over issues, bringing the total to 120 issues for Sprint 13.
I really appreciate if there is a way to find this using JQL or eazyBI report.
Thanks in advance!
You would like to use a calculation in eazyBI to check if the issue currently in this sprint was in the previous sprint as well. Here is an example formula for this:
CASE WHEN
[Sprint].CurrentMember.Level.name = "Sprint"
THEN
NonZero(SUM(
Filter(
Descendants([Issue].Currentmember, [Issue].[Issue]),
-- issue is in current/last Sprint
[Measures].[Issue Sprint] = [Sprint].CurrentMember.Name
),
CASE WHEN
-- issue was in the previous sprint as well
([Measures].[Transitions to],
[Sprint Status].[Active],
[Sprint].CurrentMember.PrevMember) > 0
THEN
-- count it in and validate with any other selections in report
[Measures].[Transitions to issues count]
END
))
END
There is a similar topic in eazyBI community portal with a bit more advanced setup to cover cases when an issue was moved over several sprints.
Daina / support@eazybi.com
When an issue goes into a sprint, the sprint gets named on the issue, and it remains there when issues go into the next sprint, so you could write:
sprint = "sprint 12" and sprint = "sprint 13"