Lluís Barbal October 11, 2023

Hi all,

I need to add a transition screen where the user is able to set the time spent and the time remaining. I do not why but the time spent does not show. I have set a simplified scenario to make some tests but I have not been able to succeed.

1.- I have created a new window with only the time tracking field.

Picture1.png

2.- I am using the default flow adding my screen to the default flow

3.- I have configured the project to use Original Time Estimate and time tracking using Remaining Estimate and Time Spent

Picture3.png

4.- I can see the estimation fields in the issue window and can log time spent.

5.- I am in the admin group and I have also added myself in all the project roles for the test

When the transition screen appears only the original estimate and Remaining Estimate is shown.

Picture4.png

Do you know what I am missing? Any hints? Thanks

Lluis

 

2 answers

2 accepted

2 votes
Answer accepted
Seifallah Bellassoued
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 11, 2023

Hi @Lluís Barbal

 

In your case you should add "Log work" field on the screen instead of time tracking.

 

Best Regards,

Seif,

Lluís Barbal October 11, 2023

It worked like a charm. Thanks!

Like Seifallah Bellassoued likes this
Seifallah Bellassoued
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 11, 2023

welcome :)

0 votes
Answer accepted
Valerie Knapp
Community Champion
October 11, 2023

Hi @Lluís Barbal , thanks for your question.

Do you mean that you want to be able to see the hours worked? For this, you would also need to add the 'Log work' field to the screen. Time tracking show, as you see, the estimates and their current state, but to be able to reduce the Remaining Estimate with the time you have spent, you need to add the 'Log work' to this screen.

Please can you test this and give us your feedback if it solves the problem?

Thanks

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events