Trigger Multiple Plans when releasing a version in Jira

Krishnanand Nayak
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 1, 2018

As part of our release process, we have 4 different module that need to be released at the same time. This means we have to trigger 4 different Build Plans when releasing the version or a way to associate these with the version to be released. So the question - Is it possible to achieve by modifying the attached screen:

image.png

1 answer

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 2, 2018

You will need to modify the code for it. Having said that, there might be a workaround.

Can you create a parent build and then make those 4 builds as child builds using build dependencies? That way, you can just trigger the parent build and that will initiate the other 4 builds.

Not sure if that is something you can use but worth exploring the dependencies.

Krishnanand Nayak
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 8, 2018

Hey Jobin... thanks for the response. let me try this and looks like it can solve our issue. i will get back if it doesn't.