Hi All,
is it possible to create two different burndown charts which can retrieve the data from from the same project and the same workflow, the real issue is, one team want to include the whole workflow including the testing statuses but other team would like to have a burndown chart which should only query the issue from open to development (not to the end of the workflow) ??
Hello Vineet,
You can certainly do that! All you have to do is make a copy of the current board. On the copy, place "Development" as the final status (place it in the "Done" column) and remove the unnecessary steps. On the copy board, you can now run a burn down report that will consider "Developed" items as done.
Let me know if you have questions!
Kian
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.