I used to be able to start sprints, now it looks like I can only complete them.
I checked all my permissions, I have manage sprint permission for every project.
Any ideas?
If you don't have parallel sprints enabled, you cannot start a sprint on a board if that board already has an active sprint associated with it.
Here is an article that explains how to enable parallel sprints:
https://support.atlassian.com/jira-software-cloud/docs/use-parallel-sprints/
Note that this is only available if you are using Company-managed projects. If you're using Team-managed, you cannot enable parallel sprints