Unfinished stories move to top of backlog at Sprint close?

S J March 5, 2020

When unfinished stories are moved to the backlog at sprint close, do they automatically go to the Top of the backlog ?

1 answer

1 accepted

2 votes
Answer accepted
Ste Wright
Community Champion
March 8, 2020

Hi @S J

These issues go back into the backlog based on their ranked order against all the other issues - which isn't necessarily the top.

If you want these issues separated and clear, create another sprint before the last one ends and move the incomplete issues into it instead of to the backlog.

Ste