Need to change an original estimate on a Story after work has been logged.
In the last quarter, we have encountered two situations where time was entered in minutes accidentally, instead of hours. It was not noticed until the end of the Sprint.
I am not asking to change Agile or Jira philosophy or defaults within the Jira system, I just need to change the original estimate because it was accidentally entered incorrect. Is there a way for a "quick fix" for accidents?
Your help is sincerely appreciated.
Mark
Hi @Mark Entrekin,
To edit the Original Estimate:
If the field Original Estimate is not found on the edit screens, then:
Hey @Mark Entrekin
The only way for you to be able to edit the Original Estimate value after work has been logged on them, is by disabling Legacy Mode on Jira.
Please contact your JIRA administrator disables Legacy Mode on Time Tracking. :)
Let me know if this helps!
Gabi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.