Upgrade JIRA Software Server version from 8.1 to 8.9

Jenny Alvarez
Contributor
June 8, 2020

Since we have not started officially the issue management yet with our JIRA, I think it is the best time to upgrade to JIRA latest version (from 8.1 to 8.9).

Current Setting:

- Added custom field setting, set dashboard, permissions, notification and registered users.

- Email notification is not set up yet

- DB is still H2 database.

- Add-ons: In Product Translation for Jira and JIRA Calendar Plugin

Questions:

1. Can we upgrade the version directly from 8.1 to 8.9?

2. Do I need to download 8.9 instance and install overwriting 8.1?

3. May I know your thought on this upgrade? Have you encountered setbacks when you upgrade to latest version? Do you have recommendation for other versions?

 

1 answer

1 accepted

0 votes
Answer accepted
Benjamin
Community Champion
June 8, 2020

HI @Jenny Alvarez ,

 

I recently upgraded from an earlier version of 8.X. No issue.

Should start using a different database, if you are using it more than an evaluation. Possibly Postgres or mysql. Jira server has a feature to see if your system is prepare for the upgrade. Should take a look at the first before upgrade.

 

You can find the instructions here to proceed. This is exactly what I did to successfully upgrade:

https://confluence.atlassian.com/adminjiraserver/upgrading-jira-installer-938846937.html

Hope this helps.

 

If you are running your server virtually, even easier. You can save the instance and reload the instance backup if it doesn't work. 

 

Thanks,

 

Ben

Jenny Alvarez
Contributor
June 8, 2020

Hi @Benjamin

Good to hear that there is no issue for 8.X version up.

About the DB, yes, we will connect to different database soon.

Thank you!

Benjamin
Community Champion
June 8, 2020

@Jenny Alvarez - You most welcome. Good Luck! If there is any questions that come up, feel free to post again on the community. 

Like Jenny Alvarez likes this
Jenny Alvarez
Contributor
June 14, 2020

@BenjaminMay I ask you how long did it take to complete the upgrade? Or is it zero downtime?

Benjamin
Community Champion
June 15, 2020

@Jenny Alvarez - There is relatively small downtime since I needed to shutdown Jira to perform the upgrade. So best to do this off hours. Also, give yourself sometime to troubleshoot if needed. Took me approximately around an hour or maybe less. If was relatively quick to upgrade once you have done the prereqs. 

Suggest an answer

Log in or Sign up to answer