Example: I have a User Story with 5 Sub-Tasks. I give the Sub's each 1 Story Point. The Parent should aggregate the Points from its Sub's to reflect the over all effort. Then, as Sub's are resolved, the reflection of that should be in the Burndown.
As it works now, only resolving the Parent will burn down the Story Points. Pretty silly. This can't be correct behavior, still....
Hi @Dave Collins & @Melanie Hoole,
The latest version of our Great Gadgets plugin offers this. The sprint and release burndown gadgets have an option to include sub-tasks, which you could use to achieve this. The plugin is available for both Jira Server (https://marketplace.atlassian.com/apps/1218777/great-gadgets-for-jira-server?hosting=server&tab=overview) & Jira Cloud (https://marketplace.atlassian.com/apps/1216564/great-gadgets-for-jira-cloud?hosting=cloud&tab=overview).
Danut.
I have the same issue. Did you find out an answer for this at all Dave?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.