Is there a way to have the velocity report display and average over the last 3 sprints? In starting up a new project it will take some time to establish the average velocity to use in sprint planning and having an average displayed on the report would be helpful.
Hi Jerry,
I've noticed this to...the velocity report has everything it should EXCEPT for the actual velocity of the team. It leave it up to the user to calculate out the value.
There is an open request for this, and I I added my thoughts of what the User Story should look like.
I suggest reviewing the ticket and adding your vote here: JSWCLOUD-16365
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.