Hello @Paulina Mijal
The Velocity Chart shows you the commitment at the moment the sprint is started, and the completed work at the moment the sprint ended. It is looking at all issues in the sprint at those two moments.
Changing the scope of work after the sprint starts will not affect the Committed metric for the sprint. All issues in the sprint will be considered for the Completed metric at the end of the sprint; it doesn't matter if the issue was added after the start of the sprint or if the scope for an issue already in the sprint changes.
https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-velocity-chart/
Yes, scrum reports will show scope change.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.