In order to make stakeholder more aware of the due date, would like to add countdown from the due date, 15 days before.
it will be visible in the ticket and in the view columns.
1. is their such plug in .
2. could we put rules on the display
Hello @Carla Bismuth
I think Pramodh M's idea - of using Atlassian Automation - is a great idea. But the duration in the WBS Gantt chat takes into account holiday calendars. Atlassian Automation cannot reference holiday calendars in the WBS Gantt Chart.
The WBS Gantt chart has an alert mark that turns green when the Start Date is approaching, yellow when the Start Date has passed and remains open, and red when the Finish Date has passed and does not close.
The WBS Cloud version allows you to customize this, so why not an alternative to the countdown?
Unfortunately, this is not implemented in the Server version. If it would be useful to you to implement this feature in the server version, please register your feedback on our product board.
Best Regards,
Akira
Ricksoft Support Team.
You can do it via Atlassian Automation using scheduled trigger to calculate the number of days ( to edit the custom field in automation by adding an action to calculate the number of days using smart value now() - issue.due date
Let me know if this helps
Thanks,
Pramodh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.