I have 2 phases loaded into Jira for my project and I've created a Gantt chart with those 2 phases.
I just added a 3rd phase by loaded additional issues that were picked up in the Gantt filter and I now have 3 phases in my Gantt. They are all at the same top level.
When I try to move my whole 3rd phase by changing the dates of the parent task on the 3rd phase, the change cascades into the 2nd phase. The phases are in no way linked. I even exported the data and verified there were no linkages between the phases.
Why would this be happening?
Thanks for your help. Our users have been saying their dates keep changing and they haven't done anything and they are losing confidence. This is the first time I'm seeing something happen that shouldn't be happening.
@[deleted]
Did you find what's causing that? I think we're having the same problem and did not figure out why that is happening
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.