What variable in Jira is controlling the sorting of Issues in the Timeline view. I have a Task level item with an associated Sub-task, and I want the Task and the Sub-task to be grouped in the Timeline view. See the image below.
Hello @Elliot Manuel
For clarity, can you provide more information as follows?
There are multiple Timeline functions in Jira:
Which of these timeline functions are you using?
Issues are typically ordered by Rank (i.e. relative priority), but it may be possible to change that depending on how you accessed the Timeline feature.
Can you open the issue you have identified as a Subtask and show us the breadcrumbs that display above the Summary for it? Example:
I believe it's sorted by issue key, therefore created order - aside from issues with parents (in JSW) which show under their parent, but also in issue key order.
You can drag/drop them into a different order, but there's no sorting option at this point.
See this help page for more information...
Reorder items on the timeline
Select the item name and drag it up or down to reorder it. If the item has child items (or subtasks), they’ll remain with their parent item. Your changes will be reflected in the board and list views as well.
Currently, you’re unable to sort in the timeline view.
Ste
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.