What is the best way to modify planned time?

Carlo Bonamico November 14, 2012

I am planning developers activities with Tempo, which requires me to plan items like:

PRJ-8 4 hours a day from 15/11 to 30/11.

That's fine, but often I need to revise planning because an activity has been delayed, and, for instance, I would like to modify the previous entry into

PRJ-8 4 hours a day from 20/11 to 07/12.

Currently the only way I found is to delete the old planning and re-enter it. Is there a better way? e.g. to "move" or "edit" the existing planning?

Thanks

1 answer

1 accepted

0 votes
Answer accepted
Sverrir Tynes [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 22, 2012

Hi

You can edit the description and date for a plan. You can not edit date range so in your case you need to delete the plan and add a new one.

We are aware of this behavior and are working on some improvements.

Best regards

Sverrir Tynes
Tempo support