What is the reason portfolio for jira does not work with sprints that have overlapping dates?
We got an answer when they updated and you have version 2.0 to 2.27:
Portfolio for Jira now lets you accurately schedule the work of teams that are sharing a board, and are working in parallel sprints.
Conflicts happen when there are overlapping start or end dates across the active parallel sprints, or when one sprint ends and another sprint starts on the same day.
When such conflicts happen: