What is the sprint capacity vs team capacity in Advanced planning?

Adam Bang
Contributor
October 15, 2024

For Plans I can set a Sprint Capacity and a Team Capacity, is it either/or when determine capacity or how is it designed that these capacities influence each other?

1 answer

1 accepted

1 vote
Answer accepted
Marc - Devoteam
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 15, 2024 edited

Hi @Adam Bang 

You can set Sprint Length and Capacity

Sprint Length should be equal to the sprint length used when creating a sprint in a scrum project.

Capacity is the total of average completed number of Story Points by a Team when executing a sprint.

So historically you can check your average story points completion number per sprint and set this the capacity of the team.

Screenshot 2024-10-15 at 17.25.41.png

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events