When i try to complate sprint, it says "issues were uncomplated"

Volkan kiper January 24, 2022

2.pngHi

İ try to complate active sprint, All issues are Done status but when complate sprint, issues are incomplate and that issue will romeve other sprint or backlog , what should i do about  make issue complated

 

My project is Company-managed  software1.png2.png

2 answers

2 accepted

2 votes
Answer accepted
Sukruth M S
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 24, 2022

Hey , @Volkan kiper , as per your query, please make sure once again that all issues are in the done status, because some issues might be in unmapped status so map them to done column and then try completing the sprint.

You can check for unmapped status in the columns in board settings.

status unmapped.png

This is the unmapped status and it has one issue which is incompleted, so you are getting  issue as not completed while completing the sprint so map it to done column and then your issues will be completed and you can complete the sprint.

Hope, this helps you @Volkan kiper 

Thanks,

Sukruth M S

Volkan kiper January 24, 2022

Thanks @Sukruth M S 

But all issues are in done status and there aren't unmapped issue

 

1.png

Sukruth M S
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 24, 2022

Hi @Volkan kiperAll great what you have done but I can see the Done column is in the (In progress category a blue line) and Blocked Column is in the (Done category a green line), Jira has categories To do, In Progress ,Done. You can complete the sprint by moving all issues to Blocked column and that helps you in issue completion and also sprint completion.

Hope this helps you, Thanks @Volkan kiper ,

SUKRUTH M S

Volkan kiper January 24, 2022

Hi @Sukruth M S 

i missed this. Now it is working. Thank you again.

Many thanks

Like # people like this
1 vote
Answer accepted
John Funk
Community Champion
January 24, 2022

Hi Volkan,

For issues to be considered complete in a sprint, they must be in the last column of your scrum board, regardless of the status. For your screen shot above, please move the Done column to be the last column (to the far right) on your board. 

Volkan kiper January 24, 2022

Yes i did it many thank you

Like John Funk likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
TAGS
AUG Leaders

Atlassian Community Events