When we export data from Jira Issues, we have a column named Original estimate

R
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 30, 2022

When we export data from Jira Issues, we have a column named Original estimate. I understand the meaning of this column but I can't guess the units use

For exemple, on Jira, the original estimate is 1d4h but in the excel download its 43200. But it's not corresponding with a conversion in minutes either in seconds

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 30, 2022

Welcome to the Atlassian Community!

It is actually seconds, but not just plain seconds, it's taking into account your settings for time tracking.

With 60 seconds in a minute and 60 minutes in an hour, you can convert to hours by dividing it by 60 twice (or by a single division of 60*60)

So, 43200 / 3600 = 12 hours.

I think your time tracking is probably the default of working time is "5 days a week, 8 hours a day".  In those terms, 12 hours = 1d 4h...