Hi,
We would like to be able to tell:
Currently working with Portfolio addon and each team manages their sprints.
Problem is that people feel like they need to work for the tool.
Anyone who works with both and can share their experience?
Any suggestions for other addons/methods?
Thanks in advance
Hi @Tal Kdoshim,
have you thought about Big Picture? It tries to calculate a bit less than Portfolio. While it's a great tool, this is not the first time I've heard something like that. It tends to do lots of things automatically, leaving teams and/or managers to feel they are not in control.
Let me know why you didn't go with Big picture and we could start a conversation.
According to the person in my org who decided to go for Portfolio, the problem with Big picture was that in case a task is delayed it will not automatically shift other tasks considering resources and dependencies.
I'm not sure it's correct.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tal, you've got a couple of tools suitable for the 'next quarter planning' in BigPicture - the Gantt chart and the roadmap. When you talk 'start and end dates' you probably mean the Gantt chart.
And yes, a delayed task, when shifted, will move forward other tasks linked to it, as long as the default 'Auto mode' is enabled in the Gantt chart module, as opposed to the Manual/Lock modes. https://wiki.softwareplant.com/display/DOCUMENTATION/Data+Display+and+Editing#DataDisplayandEditing-TaskModes
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.