Cards that are marked as “done” are being moved to the sprint after the previous sprint is completed. The workflow for our cards is as follows 

 

to do > in progress > PR review > QA review > done

 

so they seemingly should not be moved to the next sprint based on what I’ve read. 

2 answers

2 accepted

1 vote
Answer accepted
John Funk
Community Champion
July 26, 2024

Hi Kevin - Welcome to the Atlassian Community!

The issues must be in the last column on the Scrum board (far right) regardless of what Status they are in. 

Kevin Blake July 26, 2024

The done status is the last column.

Like John Funk likes this
John Funk
Community Champion
July 27, 2024

What issue type are these cards? Is it all of them? Or just some?

Kevin Blake August 2, 2024

all of them

Like John Funk likes this
John Funk
Community Champion
August 3, 2024

So all cards in the last column of the scrum board are being moved to the next sprint when you close the sprint? 

It that's the case, you need to open a support ticket with Atlassian for their help. Please post the resolution back here so we can close this one out. 

Good Luck!

https://support.atlassian.com/contact/#/

Like Dick likes this
John Funk
Community Champion
December 12, 2024

@Kevin Blake Echoing what Dick said - from your screenshot, the Done status was NOT in the last column. That will fix your problem. 

1 vote
Answer accepted
Dick
Community Champion
July 26, 2024

Hi Kevin,

Please share a screenshot of the board configuration page, tab columns.
It will give us the opportunity to see whether you're having a scrum or kanban board, and also if your status flow matches Jira's

Kevin Blake August 2, 2024

jira screenshot.png

Kevin Blake August 2, 2024

jira workflow screenshot.png

jc lazo
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 10, 2024

Any updates on this? im following this because it is also happening in the team i am currently managing.

tickets with DONE status are being carried over to the new/next sprint. please provide answers on this as this is a lingering concern for us for quite some time now.

Thanks!

Dick
Community Champion
December 11, 2024

Hi @Kevin Blake 
From the top picture you posted, "done" isn't the last column in your board, like you told @John Funk . 

I understand the pressure you're feeling as you're currently encounter this problem with your team. To take things into your own hands, I would re-suggest John's approach:

  • Have you tried his solution, putting the "done" column in the far right?
  • If this didn't help you: Have you filed a ticket at Atlassian for this?

Hope you get it working like it should,

Dick