Instead of appearing in the Roadmap Backlog some of the epics assigned to only one team appear under shared Team Features in Easy Agile. How should we fix it?
Hi there!
My name is Henri and I’m a support engineer here at Easy Agile.
It sounds like there are already epics on your Increment Roadmap that you didn't put there.
Epics are added to the Increment Roadmap in two ways:
Since you didn't add them and they're in the "Shared team features" swimlane, it's likely in this case to be date syncing.
Can you please check if:
Kind regards,
Henri, Support Engineer @ Easy Agile
Hi Henri,
The function "Date syncing is enabled for this Program, and the app finds epics have dates on them indicating they're during this Increment. (In this case, they're added to the "Shared team features" swimlane since the app does not not select a team for them.)" cause us trouble to manually every features (in my case Epic) to specific team swimlane while it is absolutely located in the team's project board.
Could you provide more advices?
Thanks
Châu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Châu Nguyễn
I'm sorry that the default swimlane for date-synced issues is causing problems for you and your teams.
Can you please share what Roadmap issue source is configured for this Program?
Kind regards,
Henri, Support Engineer @ Easy Agile
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
That's my bad not to choose correct option when created the Program.
However, we can't changed it once created. This get us to create a new program to fix it.
Tell me if we could do better.
Thanks so much,
Châu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Châu Nguyễn
You're correct that it is not possible to change the Roadmap issue source after a Program is created.
In order to switch to "Jira epics from my team boards" so that the app can assign epics to the correct team swimlanes, you would need to create a new Program.
Kind regards,
Henri, Support Engineer @ Easy Agile
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.