Hello !
So - I noticed that the stories which are marked closed are moved over sprints, did check the work flor and columns, we mapped them right but still this is happening.
Hi Krishna,
The completed issues in a Sprint must be in the far right hand column of your board, regardless of the the status type or name. Only issues in the very last column will be considered closed. Otherwise, they will carry over to the next Sprint.
Nothing gets moved to new Sprints automatically in the background. So once you end a Sprint, are you asked what to do with the incomplete tasks? Options are backlog, Future Sprint or new Sprint.
Have they all been moved to the most right column on the board? Otherwise they are not considered "complete". Do they have a resolution set?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.