According to the documentation -->
But we have observed that the issues assigned to active sprint are also being updated during Auto-schedule. Is this a bug?
Hi @NAYANA
Are the issues that were overwritten are previously estimated or un-estimated?
Documentation:
Note that if an issue is unestimated, and it's currently assigned to a sprint, release, or team, these values will not be overwritten, even if you choose to overwrite all issue values for your auto-schedule settings.