The original estimate is 3h 48m. So why does Jira show "37m over the original estimate" in case of the yellow/orange bar?
This 37m is equal to one of my logs actually.
@Kevin It seems time is getting tracked from all subtasks to this parent tasks.
The issue you are facing happens when instead of giving original estimates to issue first, we directly log work to that ticket.
In other words, there is/are some subtasks where original estimate is not present but worklogs are there.
Thanks for the tip but actually, the strange thing is, there is no subtask associated this this issue. So I'm not sure why this could be happening.
What's also really weird is that if I delete that 37 minutes long worklog, suddenly the rest of it becomes orange and it still says 37 minutes.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Kevin in that case is it possible to get screenshot of worklogs for this issue?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hey @Suvarna Gaikwad
Sorry for my belated response. Let me show you what it looks like now:
Interestingly in the worklog it appears correctly:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.