Why does my kanban board not remove items after the specified 2 weeks?

Gile Empey January 17, 2023

I have a kanban board that has a "Done" column with statuses properly mapped to them. However, items are still showing after it's been 2 weeks. We are using fix versions and releasing them. I removed the kanban board sub-filter as I wanted it to show all items once moved to a done status for 2 weeks. Do I need add something this in the sub filter to get this to show properly?

3 answers

2 accepted

0 votes
Answer accepted
Florian Bonniec
Community Champion
January 17, 2023

Hi @Gile Empey 

 

What do you have configured under the Kanban config (Hide completed issues older than)?

Gile Empey January 17, 2023

2 Weeks is what I have it set to.

Like Nancy Corsi likes this
Florian Bonniec
Community Champion
January 17, 2023

That means your issue do not match the rule you set, someone may have updated the issue since you transitionned the issue to the last column.

 

Regards

Like Nancy Corsi likes this
Florian Bonniec
Community Champion
January 17, 2023
Like Gile Empey likes this
0 votes
Answer accepted
Trudy Claspill
Community Champion
January 17, 2023

Hello @Gile Empey 

You said you removed the subfilter, so I'm assuming this is a Kanban board for a Company Managed project.

Is the Done column the one farthest to the right on the board?

Do you have the Hide Completed option set?

Screen Shot 2023-01-17 at 1.58.59 PM.png

Have the issues been updated within the past 2 weeks? The hiding is based on the Last Updated date for issues in the right-most column. If the issue has been updated in some way in the past 2 weeks it will not be hidden.

Gile Empey January 17, 2023

@Trudy Claspill Correct. The "Done" column is the farthest right and the Hide completed items is set to 2 weeks. 

The item in questions was moved to a "Resolved" status on 12/15/22 @ 8:57am and the last updated date is 1/11/23 @ 9:34am. Are you saying that since this item was updated, even though it Resolved, it is showing up in the column still?

If that is true, would there be a way to ignore update dates and just look at the status only?

Trudy Claspill
Community Champion
January 17, 2023

Yes, if the item was updated within the past 2 weeks, it will be shown in the right-most column.

There is not an option to ignore Updated dates when hiding "completed" issues. 

There is a change request about that here:

https://jira.atlassian.com/browse/JSWCLOUD-21897

As a work around you could add a quick filter that, when activated, would hide issues with a Resolved date more than two weeks in the past.

Gile Empey January 17, 2023

Interesting...I assumed it was based off of it transitioning it to the "resolved" status. We tend to have items that get comments on them after it moves to this status for maybe updating labels or other custom fields on the tickets.

Seems silly that if a year from now, someone decided to add a comment on a Resolved ticket that it going to show back up on my done column in the kanban board. 

Thanks for the info!

0 votes
Raimon Colmenares
Contributor
January 17, 2023

Thank you, I had this same issue.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events