Hello,
I'm working on JIRA Cloud, team project manage and i can't add Story Points on my ticket type.
I have only the Story Points Estimate and i don't know why my burndown is not working with SP Estimate.
Someone to help please ?
Regards,
Hi @Simon Chauvin Welcome to the Atlassian Community!
Team-managed projects use the "Story point estimate" field and Company-managed projects use the "Story Points" field.
Ok thanks for your answer.
Now how can i use burndown chart with Story point estimate ?