Hello,
My organization is exploring the capabilities of Jira Portfolio. During said exploration, an organizational roadmap was created that pulled from two separate Portfolio plans. The below image illustrates the schedule for this roadmap.
Can anyone explain why the Credit Visibility Dashboard task is duplicated? It represents a singular task being pulled from a singular project. It has two components - which we filter on to delineate issues with one component or the other in the two aforementioned boards, but I do not understand why that would cause the task to appear on the roadmap twice
Hi @Nicholas Hubbuch ,
The task appears twice on the roadmap, but under 2 different plans. This is because the task has been added to both of those plans. It shows on the roadmap twice so that you can see it in the context of each plan.
Hope that helps.
Thanks,
Clare
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.