Will Not Implement status will not allow Sprint to close

Jeff Murray June 15, 2023

Hello -

The Will Not Implement status is not allowing us to close the sprint. We currently have to change the status to Done to close the sprint.

Thanks,

Jeff

 

 

1 answer

1 accepted

3 votes
Answer accepted
Trudy Claspill
Community Champion
June 15, 2023

Hello @Jeff Murray 

A status does not block the closure of a sprint. The status just determines if the issue was considered completed in the sprint or not completed.

Only issues in the statuses mapped to the column farthest to the right on your scrum board will be considered "completed" issues. Issues in statuses in any other column will be considered "incomplete".

So, if you map the "Will Not Implement" status to the farthest right column, then those issues will also be considered "completed" when you close the sprint.

Jeff Murray June 16, 2023

Thank you, I've updated per your recommendation. 

Trudy Claspill
Community Champion
June 16, 2023

Please let us know if that resolves your issue, and if it does please consider marking the Answer as Accepted.