Workding Days Change

Sara Creenan (M&T)
Contributor
February 5, 2024

We recently noticed our standard working days change from Monday to Friday to Monday to Sunday.  Is there a way to change this for all of our existing boards in the backend so that teams do not have to individually change it?

1 answer

0 votes
Nikola Perisic
Community Champion
February 5, 2024

Hi @Sara Creenan (M&T) 

Yes, in order to do this:

1. Go to three dots of the board and click on Configure Board

2. Navigate to working days

Screenshot 2024-02-05 at 16.20.10.png

You can also set the non-working days as well.