Abraham Georges October 2, 2017

I am going nuts with this issue, is it a bug or what? Please see this image, I keep getting it all the time. I even created a brand new project and same issue.

 

P.S. How do I know which screen I should select? Create issue or Edit?

 

1.png

1 answer

0 votes
Alex Christensen
Community Champion
October 2, 2017

I think the answer here from Christian Czaia might help you.

Hi,

in your case you're running into a known issue. You can't add outgoing transitions to final statuses.

If you want to work your way around this: 

  1. Create new workflow as a copy (that way it will be inactive)
  2. Add in all the transitions you need
  3. Associate the workflow with your scheme and the issue types again to activate it
  4. Run through the wizard
  5. Done

Another thing you can't do on active workflows (drafts) is to delete statuses

Abraham Georges October 2, 2017

I am kind of a newbie on Jira, how do I create the copy and do that? I guess the goal is to replace the current workflow with the copy at the end.

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 2, 2017

Go to Admin -> Workflows and find the workflow you want to amend.  To the right, you'll have a "copy" link.

Yes, your guess about the goal is spot on.

Abraham Georges October 2, 2017

It worked!! Will get back if any other issues. So I guess the final thing is - how to replace the original one with the copy?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 2, 2017

Admin again, then look for "workflow schemes" this time.

Have a look at the project, find the workflow scheme the project is using, make a copy of that, then go into the copy, and change the old workflow for the new one you've just made.

Then go back to the project admin and change the workflow scheme to the new one.  You may need to go through a migration exercise, if you've removed status from the new one.

Abraham Georges October 5, 2017