Hi,
i am not getting the workflow management worked as it should be.
In workflows in jira settings i see that a workflow is assigned to a project,
but when in the projectsettings it is a different workflow that is assigned.
So i can't remove the "unused" workflow.
What am i doing wrong here ? it seems i get different information in different screens.
kind regards,
Kurt
maybe share screenshots of what you are seeing. In Project settings > workflow that should illustrate all workflows for the project. You should not see a discrepancy in the Jira settings > workflows area. BTW, you delete workflows only when they are under the Inactive section at the bottom of the Jira settings > workflows area. If the workflow you want to delete is in the active area you cannot delete.