Karthik Kaliki (EXTERNAL) December 31, 2022

Hi All,

I have workflow 'All statuses can transition to 'Done' but this is not working, when i tried to move the issue 'Sit' status to 'Done' popup showing updated but issue not moving into Done status. Can some one help me on this issue.

workflow_issue.PNG

 

 

5 answers

1 accepted

2 votes
Answer accepted
Karthik Kaliki (EXTERNAL) January 2, 2023

Issue was resolved by manually adding missing post functions in Done status, Actual done status have only 2 post functions instead of 5. 

2 votes
Karthik Kaliki (EXTERNAL) December 31, 2022

Hi Jack/Vikrant,

History not showing updates 

No conditions for workflow, condition showing 0 and validator showing 0

Other statuses working fine except SIT and Requirement Gathering. 

It was not working in Progress to Done as well but after project re-index this status working fine.

This workflow exported from Jira Cloud to Jira server. 

0 votes
Craig Nodwell
Community Champion
December 31, 2022

Is there any post function in the SIT or Requirement Gathering transitions that are not being met?

Karthik Kaliki (EXTERNAL) December 31, 2022

Hi Craig,

I can see below post functions and not sure about this post functions

Post_cond.PNG

Jack Brickey
Community Champion
January 2, 2023

Those are all normal default PFs.

0 votes
Jack Brickey
Community Champion
December 31, 2022

Hi @Karthik Kaliki (EXTERNAL) , a few thoughts here...

  1. check the history tab to assess any clues
  2. check the workflow for any conditions or validators that might be on the transition into Done
  3. Can you transition to Done from other statuses? If you transition into UAT and attempt into Done.
Karthik Kaliki (EXTERNAL) December 31, 2022

Hi Jack

History not showing updates 

No conditions for workflow, condition showing 0 and validator showing 0

Other statuses working fine except SIT and Requirement Gathering. 

It was not working in Progress to Done as well but after project re-index this status working fine.

This workflow exported from Jira Cloud to Jira server. 

Jack Brickey
Community Champion
December 31, 2022

What I would do here is to create a new workflow from scratch and replace the existing one. 

Like np300 likes this
0 votes
Vikrant Yadav
Community Champion
December 31, 2022

Hi @Karthik Kaliki (EXTERNAL)  Kindly check any condition and validator applied at Done transition.  

Thanks

V.Y

Karthik Kaliki (EXTERNAL) December 31, 2022

Hi Vikrant,

No conditions for workflow, condition showing 0 and validator showing 0

 