During the sprint planning meeting, we would like to assign tasks to a pair of developers and also see their workload separated for each person.
Example
We have a 2x10h task assigned to "Person 1" and "Person 2", (these are the guys doing pair programming).
On the Greenhopper Planning Board>Assignee>"Person 1" there should be 10h workload on the first person and a 10h workload on the second person.
Any ideas?
P.S. Multiuser Picker, Group Picker , addittional User picker do not work with Greenhopper
Consider creating two tasks, one for each developer and estimating them separately. Otherwise, track the combined time to one developer with a note or comment that it relates to shared time across two developers.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.