Hi Team,
We are using Scrum Board.
Epic->Story->Sub-Task's
Assumption:
Sub task's efforts should roll up to story and then epic, where epic and story efforts are mentioned as 0m, in assumption if we complete the sub-task's respective stories and epics are also getting completed in parallel.
using this way i am not getting the clear burn down chart information, what we should do. need your assistance.
You could also try the Epic Report. This shows you progress over time in a specific epic by number and story points of Stories. So again, you'd need to track at the Story level.
A burn down chart shows you how you are doing against what you committed to at the start of the sprint.
It burns down when a Story is marked as "done" - that's what you committed to and you achieved it. Either a story is done, or it is not, therefore estimates on sub-tasks are useless in burn-down. If any sub-task is incomplete, you're not "done", so you have nothing to measure.
So, you need to estimate on Stories if you want to use a burn down.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.