I've been given Manage sprint permissions, but I am still unable to Close or Start new Sprints?  Any ideas?

 

Thanks,

Eric

1 answer

0 votes
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 7, 2019

Hello,

You need the Manage sprints permission for all projects, from which the board selects issues. You can see the filter for the board in board settings -> general.